About this builder and contractor invoice template
Building jobs run for weeks and are usually paid in stages. Each invoice should say which stage it covers, and how much of the total is already paid.
What to put on a builder and contractor invoice
- Name the stage or milestone each invoice covers, and refer to the quote or contract.
- Show the total contract value and the amount already paid, using the Amount paid box.
- List variations (extra work) on their own lines and get them agreed in writing.
- Put payment terms on every invoice, and keep the dates.
Example builder and contractor invoice
| Description | Qty | Rate | Amount |
|---|---|---|---|
| Stage 1: groundwork and foundations | 1 | 4,200.00 | 4,200.00 |
| Stage 2: brickwork to first floor | 1 | 5,600.00 | 5,600.00 |
| Materials supplied by contractor | 1 | 1,850.00 | 1,850.00 |
| Total | 11,650.00 |
Example figures only. The invoice above opens with these lines already in it. Replace them with your own work and prices.
Want more choice? See all the invoice templates, or go to the main invoice generator. Save your invoice as a PDF, Word or Excel file, or print it.
How to price builder and contractor work on an invoice
Builders and contractors usually price by a quote for the whole job, by a day rate or by a cost-plus arrangement. For larger jobs, the usual practice is to invoice in stages tied to progress, such as groundwork, first fix and completion. Always refer to the original quote and to any agreed variations, so the final total is easy to explain.
Common mistakes on a builder and contractor invoice
- Not recording changes to the original quote in writing.
- Billing materials without showing receipts or a supplier breakdown.
- Leaving a retention or snagging amount unclear.
Getting paid as a builder
Stage payments protect both sides: the customer pays for progress and you are not funding the job. Put each stage, its percentage or amount and the trigger for payment on the quote and refer to it on every invoice.
Rates, tax and legal requirements differ by country and change over time. This is general guidance, not advice for your situation.
A worked example: a stage payment with a variation
On a refurbishment, you invoice stage three of the agreed schedule. An extra circuit was agreed in writing partway through, so it appears as its own variation line with the date. VAT is shown at 20%, and 5% of the total is held back as retention, as the contract allows:
| Description | Qty | Rate | Amount |
|---|---|---|---|
| Stage 3: first-fix plumbing and electrics | 1 | 3,800.00 | 3,800.00 |
| Variation 2: extra socket circuit, agreed 14 May | 1 | 460.00 | 460.00 |
| Skip hire and waste removal | 1 | 340.00 | 340.00 |
| Subtotal | 4,600.00 | ||
| VAT (20%) | 920.00 | ||
| Total | 5,520.00 | ||
| Retention held back (5%, as agreed) | -276.00 | ||
| Due now | 5,244.00 |
Example figures only. Your own prices, tax and terms will differ.
Contracts and tax treatment differ widely in building work, from reduced rates to special schemes. Treat the VAT line as an illustration only and check how it applies to your work with an accountant or the tax authority.
Where builders’ invoices commonly go wrong
The most common problem is unrecorded changes. Verbal agreements to move a wall or upgrade a fitting are easy to forget, and a customer may honestly remember them differently. Record each change in writing, give it a reference, and show it as a separate line on the next invoice.
Another is mixing stages. If the contract says payments are due at defined points, the invoice should say which point has been reached and what was completed. Customers and their lenders sometimes need this evidence before releasing money.
Materials are the third. Say whether materials are included in the stage price or charged separately, and keep receipts. A supplier’s receipt next to your invoice answers most questions.
Finally, retentions, deposits and payment terms should match the written contract. If you work with a main contractor, their terms may override yours. Dispute and payment rules for construction differ between countries, so take advice if a large sum is at stake.
Questions people ask
How do builders invoice staged work?
Invoice at each milestone, and show what has been paid so far. Use the Amount paid box for earlier payments.
What are variations?
Changes to the agreed work. Record each as its own line, agreed in writing, so there is no argument at the end.
Is anything I type sent to a server?
No. The document is made inside your browser. Your business details and the last document are remembered on this device only, so you do not have to retype them, and you can wipe them with the link under the preview.